As per previous correspondence, Balfour Beatty are carrying out minor construction works to upgrade a number of existing bellmouths (also known as access points or junctions). Dates for these works were still to be confirmed, and I am writing to now provide an update on the programme.
The bellmouths are referred to by ourselves as AP-03, AP-04 and AP-06. These works are being undertaken by our subcontractor, UB Civils, and are being completed under the Skye Reinforcement Project for SSEN Transmission.
A map is attached which shows the access points.
AP-03 – What3Words: ///those.spearhead.elated
Works in this area were scheduled to commence this week, and you may therefore have already noticed some initial activity. We are currently aiming to complete these works around 4th December.
AP-04 – What3Words: ///headed.croak.severe
Works at AP-04 are scheduled to commence week commencing 30th November, with works continuing until we demobilise for the Christmas period on 18th December.
AP-06 – What3Words: ///innovate.fancied.former
Works at AP-06 are scheduled to commence week commencing 7th December, and will include the widening for the eastern part of the existing access point. Works to continue until we demobilise for the Christmas period on 18th December.
These bellmouth/access point upgrades will allow future construction vehicles to safely move off the public road network to access the overhead line working areas, helping to minimise the impact of project traffic on other road users.
Traffic management required while the works are taking place will consist of stop-go boards, allowing traffic to safely pass the working areas. These will only be in operation while required during working hours and will not remain in place overnight or outside working hours. Warning signage will remain in place while the works are ongoing.
Commercial stone will be imported for these works. Our Supply Chain partners have been briefed to access work sites from Sligachan via the A863 and then up the B885.
Some weekend working is expected in line with our working pattern. No HGV movements will take place on Saturdays after 1pm and no HGV movements on Sunday.
We appreciate that there may be some short delays while stop-go traffic management is in operation and will aim to minimise disruption to road users as far as reasonably practicable.
The programme remains subject to change, and any significant adjustments to the planned dates or traffic management arrangements will be communicated.
If you have any specific concerns or enquiries about the works, please reach out to skyecommunications@balfourbeatty.com.
Maren is also happy to assist with any queries via skye.reinforcement@sse.com .